TIME-SEQUENCE
CONSTRAINT OF PROJECT DISASSEMBLY IN THE NETWORKED COOPERATIVE
MANUFACTURING SYSTEM
Dong Hongzhao
(College of Mechanical Engineering,
Zhejiang University of Technology, Hangzhou 310014)
Chen Ying
(The State Key Laboratory of Fluid
Power, Zhejiang University, Hangzhou 310012)
Zhao Yanwei
(College of Mechanical Engineering,
Zhejiang University of Technology, Hangzhou 310014 )
|
|
Abstract:
The
networked cooperative manufacture among enterprises can promote their
competitive capacity and the first step is to disassemble the project
into several sub-projects. There are priority constraints among the
sub-projects and their completion must follow a certain time sequence.
Here gives a new method to describe the constraints and calculate the
exact executing time area of each sub-project. The time sequence of the
sub-projects can be described by our defined before relation Rbefore
coupled with both sub-relations including serial before relation Rs-before
and parallel before relation Rpbefore. The backward deducing arithmetic
to calculate the executing time areas of the sub-projects is raised.
Moreover, the rules to determine the disassembling granularity of the
project are proposed. Eventually, the practice proved that the method
could effectively solve the time-sequence constraint issue of the
sub-projects in the multi-agent based networked cooperative
manufacturing system.
Key words:
Networked cooperative manufacture Project disassembly Time-sequence
constraint Before relation and its sub-relations Disassembling
granularity
CLC No: TH132.4 TH166